Home Application Cases Engineering and Process Package Cases Non-Stop Retrofit Project for a Municipal Wastewater Plant in Shanxi Province
Non-Stop Retrofit Project for a Municipal Wastewater Plant in Shanxi Province

Solution:Our team was responsible for the design, procurement, and installation of process and electrical equipment. The scope included cable trench excavation and laying, dismantling and restoring the fiberglass insulation cover of the original oxidation ditch, selecting aeration blowers and compatible diffusers, equipment installation and commissioning, performance testing, integrated trial runs, and final system acceptance.

Processing Scale:100000m³/d

Treatment Effect:施The construction period was 35 days. Installation and commissioning were completed rapidly without interrupting water flow, ensuring that effluent met Class A discharge standards.

Characteristics

The wastewater treatment facility was constructed in two phases.

Phase I has a treatment capacity of 50,000 m³/day and adopts three parallel Orbal oxidation ditches. Ditches A and B share a sludge selector and secondary sedimentation tank, while Ditch C operates independently with its own sludge return system.

Phase II applies the AAO process for nitrogen and phosphorus removal, also treating 50,000 m³/day.

After treatment, the effluent undergoes advanced treatment before being discharged into the receiving natural water body.


Plant Profile

Non-Stop.jpg

Option

(1) Blower Installation

Installed one 75m³/min, 90kW air suspension blower to optimize the oxidation ditch denitrification process.

(2) Aeration System Upgrade

Due to insufficient dissolved oxygen supply, retractable aeration equipment was adopted to improve oxygen transfer and allow easier maintenance and replacement.

(3) Process Commissioning and Denitrification Enhancement

Conducted process adjustments and operational tuning to strengthen nitrogen removal performance


Periodic Service

工程及工艺包项目全周期服务.jpg